ENKA retained NEOS Enerji as consultant for the root cause analysis (RCA) of a 295 MVA 400/15.7 kV generator step-up transformer failure at Gebze combined cycle power plant.

NEOS evaluated the failure evidence together with the operating and protection records, established the root cause and defined the remedial actions required.

The RCA was delivered in December 2021.