Risk, Change & Lessons Learned
Managing uncertainty and change
A comprehensive risk register, a formal deviation process and a structured lessons-learned record keep the project under control when conditions change.
Risk management
Risks are identified and assessed by category – cost, scope, time and quality – with their probability and potential impact, and recorded in a risk register together with the mitigation strategy, responsible party and current status. The register is tracked and updated throughout the project to manage and minimize project risks proactively.
Response strategies: avoidance (revise the plan to eliminate the risk), transfer (transfer the consequences to a third party through insurance, guarantees or contract terms), mitigation (reduce probability and impact to acceptable levels) and acceptance (accept the risk without changing the plan).
Risk impact scale
| Project target | Very low (0.05) | Low (0.10) | Moderate (0.20) | High (0.40) | Very high (0.80) |
|---|---|---|---|---|---|
| Cost | Negligible cost increase | Cost increase below 10% | Cost increase 10–20% | Cost increase 20–40% | Cost increase above 40% |
| Time | Negligible time extension | Time extension below 5% | Time extension 5–10% | Time extension 10–20% | Time extension above 20% |
| Scope | Minor decrease within scope | Impact on additional outputs within scope | Impact on main outputs within scope | Decrease unacceptable to management | Final deliverable rendered useless |
| Quality | Minor decrease in quality | Slight decrease in quality | Quality decrease requiring management approval | Quality decrease unacceptable to management | Final deliverable rendered useless |
Deviations and changes
All deviations from the original scope are documented with description, status and technical and financial impact. A standardized deviation request form records each change with its value, dates and comments, so that every change is properly evaluated and formally approved before implementation.
Lessons learned
Significant lessons learned are captured during the project lifecycle, organized by classification and topic with detailed descriptions and comments, and made available to improve the performance of future projects.