Energy Management System
One control core, from a single cabinet to a grid-scale plant
The NEOS EMS decides when the battery charges and discharges, keeps every unit within its limits and gives operators one view of the plant. The control logic, safety rules and data discipline are the same on every site; the configuration scales with the project.
Built into every configuration
Storage-specific algorithms
SoC balancing, constraint management and power dispatch designed around battery behaviour.
Fixed priority hierarchy
Protection and equipment safety → operating limits → grid obligations → operator → economic optimisation. Economic optimisation never overrides the layers above it.
Brand-independent integration
Driver base proven with different PCS, BMS and protection-relay makes.
Signal-quality checks
Timeout, quality-bit and stale-data checks; invalid data never reaches the algorithm.
Local operation first
Control and logging run on site; a cloud connection is not mandatory in any configuration.
Open protocols
Modbus, IEC 61850, IEC 60870-5-104, OPC UA and REST.
Defined safe state
Signal-by-signal fallback behaviour on loss of communication or loss of constraints.
Data stays with the client
Raw data is kept on the site server; export is the client’s decision.
Scalable configurations
All three share the same control core, so a site can be upgraded later without changing the control logic; the hardware list and price are fixed by this choice.
Web-based EMS
Live power flow, PCS and battery detail, scenarios, telemetry and reporting. Fast set-up, low investment, multi-site and multi-tenant access from one interface.
Typical use: single- or few-cabinet C&I sites. Grid interface optional.
PLC-based SCADA/EMS
Control runs on a PLC; a full on-site screen set – plant architecture, container and rack detail down to SoC/SoH, bulk PCS management, alarm and event handling, trends and historian – runs on the site server. Full functionality without a cloud connection.
Typical use: multi-container storage sites and industrial plants; proven at 24 containers / 48 PCS.
Redundant plant controller
Real-time RTU grid interface to the dispatch centre (IEC 60870-5-104 / DNP3), redundant plant controller for closed-loop P and Q at the point of connection, redundant servers and fibre ring, a controller per inverter, cloud historian, fleet view and predictive analytics.
Typical use: transmission-connected, grid-scale and hybrid plants with grid obligations.
| Scope / function | Redundant plant controller | PLC-based SCADA/EMS | Web-based EMS |
|---|---|---|---|
| Control core (constraints, SoC, dispatch) | ✓ | ✓ | ✓ |
| Operator interface | Web + site HMI | Site SCADA (PLC) | Web |
| Controller per inverter | ✓ | — | — |
| Redundant controller, server and network | ✓ | Optional | — |
| Plant controller and dispatch-centre interface | ✓ | ✓ | Optional |
| Historian and reporting | Cloud + local | Local | Local |
| Multi-site, multi-tenant management | ✓ | Optional | ✓ |
| Commercial module | Advanced | Basic | Basic |
| Typical commissioning time | 16 – 20 weeks | 12 – 16 weeks | 6 – 10 weeks |
Final scope is confirmed from the site data and signal list. Commissioning times from contract or advance payment.
Five control layers, from site to market
Commands flow down and measurements flow up. A layer that becomes unreachable does not stop the layers below it; each falls back to its own defined safe state.
Site equipment
PCS, BMS and battery, thermal management, fire detection, metering, breakers and auxiliary supply.
Level 0 · manufacturer device interfacesLocal control and protection
Unit controller and PLC: interlocks, permissives, fallback on invalid data, protection-relay interface.
Level 1 · Modbus TCP/RTU, hard-wired I/OPlant and dispatch control
Closed-loop P-Q at the point of connection, constraint management, SoC balancing and allocation to units.
Level 2 · Modbus TCP, IEC 61850Grid interface and site IT
Dispatch-centre telemetry, historian, reporting and operator-interface server.
Level 3 · IEC 60870-5-104, DNP3, OPC UAMarket and corporate network
Portfolio management, supplier and forecast-provider platforms; schedule and settlement exchange.
Level 4 · REST API, VPNCommercial module
The commercial module only feeds a set-point into the control core; the safety and constraint layers are unchanged. If the price spread does not cover cycling and degradation cost, no transaction is made – the threshold is set by the user.
Basic – arbitrage
Daily charge–discharge plan generated from the market clearing price or user-defined hours; applied within the SoC band, connection limit, site load and battery current and temperature limits; daily and monthly revenue, cost, captured price spread and net benefit reported.
Advanced – forecasting and ancillary services
Market price, site load and plant generation forecasts from a specialist provider; day-ahead schedule optimisation against site constraints and degradation cost; capacity reserved for frequency-control and reserve services with availability declaration and real-time tracking; schedule and settlement exchange with portfolio platforms via API.
The module generates, applies and reports schedules. Direct market bidding authority and revenue guarantees are outside its scope; forecast services, market data access and ancillary-service qualification are defined per project.
Network and cybersecurity
The control network, the operating network and remote access are kept in separate zones with port, protocol and access-control policies – VLAN separation alone is not treated as isolation. Fibre-ring topology on managed switches falls back to the alternative path on a break; a firewall separates the control network from the outside; remote access is VPN-only with personal accounts, time-limited service sessions and session logging. Default passwords are changed, unused ports and services closed, versions inventoried and updates applied in planned windows with a rollback plan; NTP time synchronisation, configuration and database backups with tested restores. The approach follows the IEC 62443 zone-and-conduit model and ISO/IEC 27001 practice without claiming a certified security level; the corporate IT network and internet access remain the client’s responsibility.